The Builder’s Right to Fix Defective Building Work: Navigating Construction Defect Resolutions

Table of Contents

7 min read

When confronted with building flaws, property owners face a critical decision: allow the original contractor to address the issues or seek alternative solutions. A thorough grasp of legal principles and insights from relevant court rulings can greatly assist both parties in managing such disagreements effectively. This article examines key lessons from two significant legal proceedings involving strata plan owners and construction firms. These cases highlight the crucial role of rationality when declining a builder’s offer to perform remedial work, shedding light on the delicate balance between owner’s rights and contractor obligations in construction defect resolutions.

Case Overview: Defective Work and Opportunity to Rectify

A legal dispute arose concerning a residential apartment building in New South Wales, involving the Owners Corporation, the construction company, and the property developer. The issue came to light in February 2014 when the Owners Corporation engaged a certified builder to assess the property. The resulting report identified 30 distinct construction flaws requiring attention.

Invoking their rights under the Home Building Act 1989, the Owners Corporation demanded the builder rectify all substandard or flawed workmanship. However, the builder only managed to address nineteen of the thirty identified issues. Despite repeated efforts by the Owners Corporation to secure a comprehensive and suitable plan from the builder to tackle the remaining defects, these attempts proved fruitless.

As the statutory defect liability period neared its end, the Owners Corporation made the decision to deny the builder further access to the property for rectification work. They subsequently initiated legal proceedings against the builder in the NSW Civil and Administrative Tribunal. The case was later transferred to the NSW Supreme Court, where both parties agreed to appoint a referee. This referee was tasked with determining the existence of defective work, outlining the necessary scope for rectification, estimating the associated costs, and providing a detailed construction timeline.

Legal Principle #1: Duty to Mitigate Loss

The primary legal consideration when assessing whether property owners can deny a builder access for defect rectification is the obligation to act reasonably in minimising damages. As a general rule, owners should provide the original contractor a fair chance to address construction flaws, thereby mitigating potential losses stemming from these defects. This principle is rooted in the understanding that, typically, it is more economical for the builder to remedy issues while still engaged with the project.

In the case under discussion, it was concluded that the Owners Corporation acted reasonably by allowing the builder an opportunity to reduce the financial impact of the identified defects. By permitting the builder to attempt rectification of the thirty documented flaws, the Owners Corporation demonstrated their commitment to mitigating potential losses.

This approach aligns with the legal expectation that those who have incurred losses should take reasonable steps to limit the extent of those losses. It acknowledges the builder’s expertise and potential cost-effectiveness in addressing issues they are familiar with, while also recognizing the property owners’ responsibility to facilitate reasonable attempts at rectification.

Legal Principle #2: Reasonable Action in Relation to Loss Recovery

When evaluating whether property owners can deny a builder access for defect rectification, it’s crucial to consider that the party experiencing loss due to a breach in a building contract must act reasonably regarding that loss to be eligible for recovery. In this particular instance, the court deemed it reasonable for the Owners Corporation to refuse the builder entry to the property for defect remediation. This decision was based on the court’s acceptance that the Owners Corporation had justifiably lost confidence in the builder’s willingness and capability to perform the necessary rectification work.

Several factors contributed to this conclusion:

  1. The builder failed to provide a comprehensive scope of work and pertinent information.
  2. The initial work plan presented by the builder was considered insufficient to address the defects as identified by the Owners Corporation’s expert.
  3. The court noted that the builder’s communications in response to the Owners Corporation’s claim were “unnecessarily confrontational”.
  4. Previous rectification efforts by the subcontractor were deemed unsatisfactory in quality.
  5. The subcontractor failed to adhere to agreed-upon schedules for work on the property and individual units.
  6. Unauthorised entry to the property by the subcontractor was reported.

This case underscores that when a builder’s conduct and responses have reasonably eroded an owner’s confidence in their willingness and ability to rectify defects, the owner may be justified in refusing further access for repairs while retaining the right to recover losses. This principle balances the obligation to mitigate losses with the right to expect competent and professional conduct from builders in addressing construction defects.

Defining “Reasonable” in Refusing Builder Repairs

The concept of “reasonable” refusal for builder repairs varies and is evaluated on a case-by-case basis, considering specific circumstances. Previous legal decisions provide guidance on determining when denying a builder access for defect remediation may be considered reasonable.

1. Eroded Confidence in Builder’s Competence and Willingness

Owners may justifiably lose faith in a builder’s ability to adequately address defects due to a history of subpar work or failed past rectifications. Legal rulings have acknowledged that owners should have the option to engage alternative contractors instead of granting the original builder unrestricted access for repairs. Cases exist where refusing builder access was deemed reasonable when the builder was found to be “clearly incompetent or hazardous”. While allowing the builder to rectify issues can minimise financial losses for both parties, the reasonableness of refusal hinges on the builder’s conduct and previous repair attempts.

2. Builder’s Denial of Defect Existence

Owners may have valid grounds to refuse a builder’s rectification efforts if the builder persistently denies the existence of defects. In such instances, owners must take reasonable steps to mitigate losses resulting from the builder’s contract breach. Courts have supported owners’ refusal when builders deny defects until late in legal proceedings. In these cases, owners were permitted to contract other professionals for repairs and seek compensation for reasonable costs from the original builder.

3. Builder’s Failure to Return for Rectification

The obligation to mitigate loss applies equally to the builder. If a builder fails to return to the site to rectify defects, it may be reasonable for the owner to deny future access for repairs. Furthermore, the builder may be liable for the cost of third-party rectification work. For instance, if a builder, notified of water ingress, fails to undertake necessary repairs or proposes inadequate solutions, owners may justifiably engage other professionals and refuse the builder’s return.

4. Unreasonable Rectification Proposal

Owners may be justified in refusing a builder’s rectification if they reasonably believe the proposed scope of work or method is inadequate or unsuitable. Disagreements over the proposed rectification approach can be valid grounds for owners to seek alternative solutions or recover losses. For example, if a builder’s proposed work scope significantly deviates from expert recommendations or if they fail to offer a suitable alternative, owners may reasonably refuse the proposal. Courts have recognized that owners are not acting unreasonably by relying on professional opinions or pursuing other rectification avenues when the builder’s proposed method is deemed unsatisfactory.

In Closing

To summarise, property owners and Owners Corporations in New South Wales may, under specific conditions, have grounds to prevent builders from rectifying defects on their premises. This decision should be rooted in principles of reasonableness and the unique circumstances of each situation.

While property owners are generally expected to minimise their losses and offer builders a fair chance to address defects, certain scenarios may justify denying the builder access. These include cases where owners have justifiably lost confidence in the builder’s commitment and capability to rectify issues, situations where the builder refuses to acknowledge the existence of defects, instances of the builder’s failure to return for repairs, or when the builder’s proposed rectification plan is considered inadequate.

Navigating the intricate landscape of strata law can be challenging, particularly when deciding whether to refuse a builder’s attempts to rectify defects on your property. It’s crucial to seek expert legal advice in these matters. Professionals specialising in strata and construction law can provide invaluable assistance in addressing building defects in New South Wales. Their expertise can help lot owners understand their rights and make informed decisions to protect their interests in complex construction-related disputes.

Related Posts

Helping Solve Your Strata Legal Matter
Is Our Mission

"Strata.Lawyer's expertise is unmatched. Their free guides helped me understand my rights, and when I needed more, their lawyers provided excellent advice. A fantastic resource for any strata owner."

Sashank Venkatesh

"I'm impressed by the wealth of information on Strata.Lawyer's blog. When I faced a complex issue, their articles gave me a starting point, and their lawyers expertly guided me through resolution."

Jennifer Lee

"The team at Strata.Lawyer combines top-notch legal services with an incredible online knowledge base. Their free resources saved me time and money, and their legal support was invaluable when I needed it."

Brenda Griffiths

Solving Strata
Problems For:

Our app allows you to get the full-service offerings of a doctors office from the comfort of your home.

Have Your strata Legal Matter Resolved By An Actual Strata.Lawyer

New Email

From: Alex, strata.Lawyer

Subject: Help with By-Laws

Hi Nicole,
I've reviewed your strata by-laws and there are a few amendments that need to be made to bring them up-to-date.
Can we schedule a time to discuss the changes?

New Email

From: Peggie, strata.Lawyer

Subject: Strata Levy Concerns

Hey Sarah,
I've looked into your query about the recent special levy. There might be some grounds to challenge it.
Shall we set up a call to discuss your next steps?

New Email

From: Raea, strata.Lawyer

Subject: Renovation Approval

Good news Tom,
I've reviewed the strata committee's decision on your renovation plans. There are a few points we can address to improve your chances of approval.
When are you free to go over the details?

New Email

From: Sharon, strata.Lawyer

Subject: Parking Dispute Resolution

Hello Alex,
I've examined the details of your parking space dispute. There are several strategies we can employ to resolve this.
Can we schedule a time to discuss your options?